      Hi,

      If the ACI measures (Base/Performance) have no results for a reporting period, then is the expectation to be null flavor or should we pick it up as zero in numerator & denominator Data?

      Also what is the expectation for the performance rate value in the scenario where there are no results obtained for the measures in 2017 performance period. Please confirm.

      Thanks & Regards
      Dr.Pooja