While parsing QRDA Cat 1 document, popHealth 3.0.0 RC1 is calculating the “cumulativeMedicationDuration” by the formula (end_date - start_date).
If the end_date is not present, then it is not calculating “cumulativeMedicationDuration”
The map logic expects a “cumulativeMedicationDuration” value to be present in patient data in records collection.We assume this to be the reason for the calculation error for CMS 179 v2 measure while testing the same in cypress 2.4.
Any inputs regarding calculations in the scenario of missing medication end date will be highly appreciated.
Thanks & Regards,
Rahul
- relates to
-
CQM-1032 Calculating medication duration for active meds with no end dates
- Closed
-
CYPRESS-196 How is "cumulative medication duration" expected to be calculated from Cypress QRDA Cat 1 test patients?