      After further review, we would like to amend our answer to provide additional information.
       
      Scenario 1: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 11/1/2017 00:00:00 start of "Measurement Period" - 2 months - 11/1/2018 00:00:00
       
      This scenario is the correct Denominator Identification period for a measurement period of 1/1/2019 00:00:00 12/31/2019 23:59:59.
       
      11/1/2017 00:00:00 is 14 months prior to 1/1/2019 and 11/1/2018 00:00:00 (or effectively 10/31/2018 23:59:59) is two months prior to 1/1/2019. This creates a 12 month (inclusive) Denominator Identification period that starts 14 months prior to 1/1/2019 and ends two months prior to 1/1/2019.
       
      Scenario 2: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 11/1/2017 23:59:59 start of "Measurement Period" - 2 months - 11/1/2018 23:59:59
       
      In order to correctly reflect the Denominator Identification period for this measurement period, which begins at 1/1/2019 00:00:00, Scenario 2 needs include the full day of 11/1/2017 (14 months from the start of the measurement period).
       
      Scenario 3: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 10/2/2017 00:00:00 start of "Measurement Period" - 2 months - 10/2/2018 00:00:00
       
      This scenario does not reflect a Denomination Period that starts 14 months from the start of the measurement period, nor ends 2 months from the start of the measurement period. Scenario 3 does not correctly identify a Denomination Period for a measurement period of 1/1/2019 00:00:00 – 12/31/2019 23:59:59.
       
      Scenario 4: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 10/2/2017 23:59:59 start of "Measurement Period" - 2 months - 10/2/2018 23:59:59
       
      This scenario does not reflect a Denomination Period that starts 14 months from the start of the measurement period, nor ends 2 months from the start of the measurement period. Scenario 4 does not correctly identify a Denomination Period for a measurement period of 1/1/2019 00:00:00 – 12/31/2019 23:59:59.
      Show
      After further review, we would like to amend our answer to provide additional information.   Scenario 1: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 11/1/2017 00:00:00 start of "Measurement Period" - 2 months - 11/1/2018 00:00:00   This scenario is the correct Denominator Identification period for a measurement period of 1/1/2019 00:00:00 12/31/2019 23:59:59.   11/1/2017 00:00:00 is 14 months prior to 1/1/2019 and 11/1/2018 00:00:00 (or effectively 10/31/2018 23:59:59) is two months prior to 1/1/2019. This creates a 12 month (inclusive) Denominator Identification period that starts 14 months prior to 1/1/2019 and ends two months prior to 1/1/2019.   Scenario 2: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 11/1/2017 23:59:59 start of "Measurement Period" - 2 months - 11/1/2018 23:59:59   In order to correctly reflect the Denominator Identification period for this measurement period, which begins at 1/1/2019 00:00:00, Scenario 2 needs include the full day of 11/1/2017 (14 months from the start of the measurement period).   Scenario 3: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 10/2/2017 00:00:00 start of "Measurement Period" - 2 months - 10/2/2018 00:00:00   This scenario does not reflect a Denomination Period that starts 14 months from the start of the measurement period, nor ends 2 months from the start of the measurement period. Scenario 3 does not correctly identify a Denomination Period for a measurement period of 1/1/2019 00:00:00 – 12/31/2019 23:59:59.   Scenario 4: Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59 start of "Measurement Period" - 14 months – 10/2/2017 23:59:59 start of "Measurement Period" - 2 months - 10/2/2018 23:59:59   This scenario does not reflect a Denomination Period that starts 14 months from the start of the measurement period, nor ends 2 months from the start of the measurement period. Scenario 4 does not correctly identify a Denomination Period for a measurement period of 1/1/2019 00:00:00 – 12/31/2019 23:59:59.
    • EP
    • Depression Remission at Twelve Months

      We have a query regarding Denominator condition of CMS159v7:

      *Denominator *
      o "Initial Population"

      Definitions

      Denominator Identification Period

      o Interval[start of "Measurement Period" - 14 months, start of "Measurement Period" - 2 months )

      Please confirm which interval should qualify:

      Scenario 1:
      Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59
      start of "Measurement Period" - 14 months – 11/1/2017 00:00:00
      start of "Measurement Period" - 2 months - 11/1/2018 00:00:00

      Scenario 2:
      Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59
      start of "Measurement Period" - 14 months – 11/1/2017 23:59:59
      start of "Measurement Period" - 2 months - 11/1/2018 23:59:59

      Scenario 3:
      Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59
      start of "Measurement Period" - 14 months – 10/2/2017 00:00:00
      start of "Measurement Period" - 2 months - 10/2/2018 00:00:00

      Scenario 4:
      Measurement Period : 1/1/2019 00:00:00 – 12/31/2019 23:59:59
      start of "Measurement Period" - 14 months – 10/2/2017 23:59:59
      start of "Measurement Period" - 2 months - 10/2/2018 23:59:59

      Please confirm which scenario is valid

            edave Mathematica EC eCQM Team