[QRDA-1254] Transition to New EHR mid-way through Quality Reporting Created: 11/20/24 Updated: 12/03/24 Resolved: 12/03/24 |
|
Status: | Resolved |
Project: | QRDA Issue Tracker |
Component/s: | Reporting/Attestation |
Type: | Question/Guidance | Priority: | Moderate |
Reporter: | Jeff Satine | Assignee: | Yan Heras |
Resolution: | Resolved | Votes: | 0 |
Labels: | None |
Issue Links: |
|
||||||||
2026 Reporting Period Hosp Inpt eCQMs: |
Not measure related
|
||||||||
2025 Reporting Period Hosp Inpt eCQMs: |
Not measure related
|
||||||||
2025 Performance Period EC eCQMs: |
Not measure related
|
||||||||
2025 Reporting Period Hosp Outpt eCQMs: |
Not measure related
|
||||||||
2024 Reporting Period Hosp Outpt eCQMs: |
Not measure related
|
Description |
One of the hospitals in our system is scheduled to transition to EPIC between Q1 and Q2 of 2025. I understand that this scenario may qualify for the Extraordinary Circumstances Exceptions (ECE) Policy. However, if the hospital prefers not to utilize one of its ECE years, are there alternative options we can explore to submit eCQM data for CY 2025? It is possible for submitting; what process should the hospital follow with their EHR vendor? |
Comments |
Comment by Jeff Satine [ 12/02/24 ] |
Yes, thank you. This answers my question |
Comment by QRDA-ICF [ 11/27/24 ] |
Hi Satinej, Does this solution answer your question? If you have no follow up questions, this ticket will be considered resolved and closed on Tuesday, December 3. Thank you. |
Comment by Yan Heras [ 11/21/24 ] |
Hi Jeff, Please take a look at the guidance provided by HQR to this issue (see the comment dated 4/15/2024) https://oncprojectracking.healthit.gov/support/browse/QRDA-1216 Hope it helps answer your question. |
Comment by QRDA-ICF [ 11/20/24 ] |
Thank you for submitting a ticket to the QRDA JIRA Issue Tracker. Our experts are reviewing your ticket and will provide feedback as soon as possible. Thank you for your patience. |