"concurrent" operator doesn't work correctly with measurement start and end dates

XMLWordPrintable

    • Type: Bug/Issue
    • Resolution: Fixed
    • Priority: Major
    • Component/s: Measure Import
    • None

      Measure logic that uses the concurrent operator with either the "Measurement Start Date" or "Measurement End Date" is parsed incorrectly. For example, logic that reads

      ends concurrent with "Measurement Start Date"

      is incorrectly parsed as

      ends concurrent with "Measurement Period"

      Two measures that exhibit this issue are CMS56v3 Functional Status Assessment for Hip Replacement and CMS66v3 Functional Status Assessment for Knee Replacement.

            Assignee:
            Unassigned
            Reporter:
            Peter Krautscheid (Inactive)
            Votes:
            0 Vote for this issue
            Watchers:
            2 Start watching this issue

              Created:
              Updated:
              Resolved: