      Hi,
      We are trying to generate quarterly QRDA III MIPS Individual report for 2016 Bundle for the 2017 Reporting Period.

      Following are the four quarters of 2017 that we have taken into consideration:
      Quarter I: 1st Jan 2017 to 31st March 2017
      Quarter II: 1 Apr 2017 to 30th June 2017
      Quarter III: 1st July 2017 to 30th Sept 2017
      Quarter IV: 1st Oct 2017 to 31st Dec 2017

      Uploading QRDA III MIPS Individual report for Quarter I (i.e. compliance period starts on 1st Jan 2017 and ends on 31st March 2017) didn't give any error. Similarly when I am trying to validate QRDA III MIPS Individual report for others quarters, I am getting the following submission error:

      * Does the start date always need to be 1st Jan 2017 ?
      * If yes then how can we quarterly report QRDA III MIPS Individual ?